T.C.A. § 7-51-2204 sets deadlines and limits for local-government review of certain development submissions. It also provides for deemed approval when a local government misses specified deadlines and establishes what happens after deficiencies are reported.
The section defines a local government as a "municipality, county, or county having a metropolitan form of government." It applies when a local government is responsible for reviewing a developer's development application, development plan, or site inspection submitted for developing real property in Tennessee.
Within 60 business days after submission, the local government must either approve the submission or add it to the next available agenda of the planning commission or governing body. Within 30 business days, local governments must instead provide the developer a written deficiencies report or request additional information necessary to ensure compliance with applicable regulations. When communicating change requests, the local government must make all efforts to consolidate changes pertaining to a single application into a single deliverable document or set of documents.
If the local government takes no action within the applicable deadlines, the submission is deemed approved. For these deadlines, a day when the local government's offices are closed for business during a state of emergency declared under Tenn. Code Ann. § 58-2-107 does not count as a business day.
If the local government issues a written deficiencies report and later receives documentation that each deficiency has been satisfactorily resolved, it must, within 30 business days, either approve the submission or place it on the next available agenda of the planning commission or governing body.
A local government may issue no more than two written deficiencies reports for a submission. If deficiencies identified in a second report are not satisfactorily resolved, the local government must either deny the submission with written justification based on specific evidence of noncompliance with one or more statutory or regulatory requirements and return 50 percent of the total fees the developer paid during the review process, or conditionally approve the submission or place it on the next available agenda for conditional approval.
If the initial submission is incomplete, the local government must notify the developer in writing within 30 business days after receiving it. That notice of incompleteness does not count as a written deficiencies report for purposes of the two-report limit.
Compliance with these new deadlines will require coordination across county departments as well as a well-documented guide for the administrative review process.